Defence projects take too long: report

The latest review of defence procurement projects shows many are taking far longer than planned.

2 min read

Published

Updated

Source: AAP


Skip to article content

Major defence projects continue to take far longer than planned, with the top 29 running a combined 957 months late - 147 months more than last year.

The latest Major Projects Report shows the slowest was the modernisation of defence high frequency communications, which ran 12 years and three months longer than planned.

That was followed by the project to upgrade the navy's guided missile frigates, which is approaching finalisation about 10 years late.

The report, prepared by the Australian National Audit Office (ANAO) and Defence Materiel Organisation (DMO), says all projects continued to operate within the total approved budget of $44.3 billion.

However, there were increases stemming from foreign exchange variations and changes in scope.

News that makes sense

Your trusted source for staying up-to-date with the world around you. Get free daily news updates and analysis, straight to your inbox.

By subscribing, you agree to SBS’s terms of service and privacy policy including receiving email updates from SBS.

"Maintaining major projects on schedule remains the most significant challenge for the DMO," the ANAO said.

DMO chief executive Warren King said schedule performance deteriorated by six per cent.

"Funding constraints in 2013-14 are likely to place further pressures on schedule performance," he said in the report.

On the plus side, DMO expects to receive full capability on all projects.

That's good news for the RAAF's Wedgetail airborne early-warning aircraft.

Concerns were expressed that its advanced and highly developmental radar would never deliver all its planned level of capability. DMO said all deficiencies should be addressed through remediation programs.

Mr King also revealed concerns about cost overruns and delays in the $8 billion project to construct three advanced air warfare destroyers for the navy.

That project exceeded its budget for the year by $106.4 million, pushing it to $725 million. That was attributed to industry participants exceeding the budget for labour, materials and sub-contracts.

DMO said there was sufficient budget to complete the project against the agreed scope.

It will commission an independent review to identify the problems and how they can be fixed.


Get SBS News straight to your inbox

Sign up now for daily news from Australia and around the world. You can also subscribe to Insight's weekly newsletter for in-depth features and first-person stories.

By subscribing, you agree to SBS’s terms of service and privacy policy including receiving email updates from SBS.

Follow SBS News

Download our apps

Listen to our podcasts

Get the latest with our News podcasts on your favourite podcast apps.

Watch on SBS

SBS World News

Take a global view with Australia's most comprehensive world news service

Stream now

Watch the latest news videos from Australia and across the world